A resurfacing project will continue improvements on Main Street starting Tuesday, September 7 and concluding Sunday morning, September 12.

It’s part of the City’s T-147 Pedestrian Safety Improvements project. The work spans from Heritage Club Drive South / Luther Lane to Scioto Darby Road. 

Main Street will not be closed but individual lane closures will occur to complete the work.  The schedule of work is as follows:

  • Tuesday, September 7, 9 a.m. to 3 p.m. – Pavement milling
  • Friday, September 10, 6 p.m. to 7 a.m. – Asphalt
  • Saturday, September 11, 6 p.m. to 7 a.m. – Final course of asphalt

Final pavement markings will be installed 7-10 days after the final course of asphalt. However, temporary paint will be applied in the meantime to accommodate traffic.