Closure: Elliott Road undergoing resurfacing

Road Closure Alert

A road closure on Elliott Road is scheduled for two weeks beginning June 10 to allow for resurfacing improvements.

The work will be completed in two phases. Traffic will be detoured for each section. The detour is Scioto Darby Road to Cosgray Road to Hayden Run Road.

Phase One: The south portion of the roadway will be paved first, beginning Monday, June 10. Work will be completed June 17 or June 18, weather permitting.

Phase Two: The north portion of the roadway will be paved immediately following Phase One. Work is expected to be complete Monday, June 24.